Paris District Road Report for Week of November 6, 2023

Paris — Here’s a look at work planned in the district for the week starting Nov. 6, 2023. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay special attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

Sherman Area (Fannin, Grayson Counties)

Contacts: Sherman Area Office (903) 892-6529; Grayson Co. Maintenance (903) 893-8831; Fannin Co. Maintenance (903) 583-7566.

Grayson County: US 75, from FM 1417 to SH 91 (Texoma Parkway). Watch for shoulder closures and lane shifts on the northbound and southbound US 75 main lanes between SH 91 and FM 1417 as crews work on building new main lanes, bridges, and retaining walls. Watch for lane closures on the frontage roads between FM 1417 and SH 91. A reduced speed limit of 60 mph on the US 75 mainlanes has been set on the mainlanes for this construction project.
Mainlane traffic has been switched from the old mainlanes to the existing frontage roads to allow for construction of the new mainlanes and bridges between South Travis Street and Center Street. During this operation, northbound US 75 mainlane traffic will shift onto the existing frontage road approximately one-half mile north of South Travis Street and transition back to the existing mainlanes at Middleton Street. Southbound US 75 mainlane traffic will shift onto the existing frontage road approximately one-half mile north of Park Avenue and transition back to existing mainlanes approximately one-half mile north of South Travis Street. This operation will allow for reconstruction of the proposed US 75 mainlanes and bridges at Post Oak Creek. During this phase, US 75 frontage road traffic will be reduced to a single travel lane while US 75 mainlane traffic will maintain two travel lanes. Both mainlane and frontage road traffic will be separated by concrete barriers.
All eastbound and westbound lanes of Park Avenue under US 75 are closed to traffic. This closure is necessary to allow for construction of the new overpass at Park Avenue. To detour, eastbound Park Avenue traffic will continue on the southbound US 75 frontage road, turn left on South Travis Street, and turn left on the northbound US 75 frontage road to return to Park Avenue. Westbound traffic will turn right on the northbound US 75 frontage road, turn left on Center Street, and turn left on the southbound US 75 frontage road to return to Park Avenue.
The intersection of North Travis Street with US 75 is closed to allow for the construction of the new northbound US 75 overpass at North Travis Street. While the intersection is closed, traffic on west- and eastbound North Travis Street will be able to turn right only onto the frontage road and detour to the next available intersection. State Highway 91, Taylor Street, Washington Street and the U-turns at Washington Street will remain open during this temporary closure.

US 75, at the US 82 intersection. Watch for lane closures and lane shifts for the frontage roads on the northbound and southbound US 75 frontage road lanes between South Loy Lake Road and Lamberth Street, as well as on the eastbound and westbound US 82 frontage road lanes between FM 131 and Loy Lake Road while crews work on construction of new frontage road lanes.
The eastbound entrance ramp to US 82 at the US 75 intersection is closed to traffic. This ramp serves as the entrance ramp to eastbound US 82 at US 75. This closure is needed to complete the construction of the US 82 eastbound frontage road and new entrance ramp. Motorists are advised to use the eastbound frontage road and continue east through the Loy Lake intersection and use the eastbound entrance ramp from Loy Lake Road to gain access to US 82.
FM 1417, from US 82 to SH 56. Watch for lane shifts and shoulder closures between US 82 and SH 56 while crews construct the new roadway pavement. The ultimate roadway will be a four-lane divided section with turn lanes. A reduced speed limit of 45 mph has been set for this construction project.
FM 121, from Main Street in Van Alstyne to SH 160. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
SH 11, from FM 697 in Sherman to US 69 in Whitewright. Watch for daytime lane closures as workers replace guardrails, backfill the pavement, and seed the project. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Park Road 20 in Eisenhower State Park. Watch for daytime lane closures within Eisenhower State Park as workers perform base repairs on the roadway and then overlay the roadway with a hot-mix surface. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
US 82, from the Cooke County line to FM 131 in Sherman. Watch for lane closures as workers replace the bridge railing and guardrail approaches at each bridge structure and install median barrier. During construction, the bridge location will be reduced to one lane while crews replace the bridge railing. Currently, the contractor is working on the westbound US 82 lanes at Harris Creek and on the eastbound lanes at Post Oak Creek. On this project, the contractor is also installing a center median concrete traffic barrier between FM 1417 and FM 131. Motorists should expect lane closures while this work is ongoing.
Crawford Road at the Tributary of Big Mineral Arm. Crawford Road at the Tributary of Big Mineral Arm is closed to through traffic to allow for replacement of the bridge. During the closure, traffic is asked to use Basin Springs Road and Brooks Lane as a detour.
US 75 full depth concrete repair. Crews will be working on US 75 each week from Sunday night through Friday morning during the overnight period. Lane closures will be present at night for crews to replace failed concrete sections. Lane closures will begin at 7:30 p.m. each night and should be reopened to traffic by 6 a.m. This work will extend from the Collin-Grayson County line to the Oklahoma State line.
US 75 debris pickup, from Collin County line to Oklahoma State line. Watch for mobile lane closures as workers pick up debris from the roadway every Sunday, Tuesday, and Thursday during the nighttime.
FM 902, from US 377 to SH 289. Watch for daytime lane closures as maintenance crews perform base repairs and blade level the roadway with hotmix. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 3133, from SH 5 to the Collin County line. Watch for daytime lane closures as maintenance crews blade level the roadway with hotmix. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Fannin County: SH 78, from US 82 to the Oklahoma State line. Watch for daytime shoulder closures and occasional lane closures as workers install sloped end treatments on drainage structures and replace bridge rail and guardrail.
FM 100, from SH 56 to FM 2216. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 271, from SH 78 to FM 68. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
CR 3210 at Bullard Creek. CR 3210 at Bullard Creek is closed to through traffic to allow for replacement of the bridge. During the closure, traffic is asked to use CR 3200 as a detour.
SH 34, from FM 64 to FM 1550. Watch for traffic shifts and traffic-signal-controlled lane closures as workers build the bridge approaches for the new SH 34 roadway at the future Lake Ralph Hall.
FM 1550, from SH 34 to CR 3544. Watch for daytime lane closures as crews work on building the connection of the realigned FM 1550 to the existing roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
SH 56, from FM 2077 in Dodd City to SH 34 in Honey Grove. Watch for daytime lane closures as maintenance crews perform spot milling on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.

Sulphur Springs Area (Hopkins, Franklin Counties):
Contacts: Sulphur Springs Area Office (903) 885-9514; Franklin Co. Maintenance (903) 537-4976; Hopkins Co. Maintenance (903) 885-4031.
Franklin County: I-30, from SH 37 to County Road 3050. Watch for single lane closures and delays as crews perform pavement widening for truck parking area.
Spur 423, at I-30 N Frontage Road. Watch for single lane closures and delays as crews install traffic signal.
Hopkins County: FM 900, from I-30 to FM 3019. Watch for single lane closures and delays as crews begin road widening operations.

Paris Area (Delta, Lamar, Red River Counties)
Contacts: Paris Area Office (903) 784-1357; Delta Co. Maintenance (903) 395-2139; Lamar Co. Maintenance (903) 785-4468; Red River Co. Maintenance (903) 427-3561.
Lamar County: Loop 286, from FM 1497 around the north loop to FM 1507. Watch for temporary lane and shoulder closures and traffic merges while crews improve guardrail and drainage structures and perform bridge maintenance.
Loop 286, from US 271 North going west to FM 79. Watch for temporary lane and shoulder closures, lane shifts, crossing closures and merging traffic while crews place a bonded concrete surface and perform asphalt paving operations.
US 271, from LP 286 to Oklahoma State Line. Watch for temporary lane and shoulder closures and traffic merges while crews resurface the pavement and perform bridge maintenance.
FM 1507 (Jefferson Rd), from SH 19 to 0.8 MI North of Loop 286. Watch for temporary lane and shoulder closures while crews install sidewalk.

CR 26320 at Morrison Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 1497, from FM 1184 to FM 3426. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures

SH 24, Lamar & Delta Counties: from the FM 64 intersection to 1,540 feet east of FM 198. Watch for temporary lane closures and lane shifts while crews resurface the roadway and perform bridge rail upgrades.

Delta County: FM 64, from FM 128 to SH 1532. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.
FM 2068 at East Fork of Jernigan Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 2675, from Lamar County line to FM 128. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.

Red River County: Cedar / Church Street (Clarksville, Texas), at the intersection of Cedar and Church Street. Watch for road closure while crews remove and replace the existing bridge.

Locust Street (Clarksville, Texas), at Delaware Creek. Watch for road closure while crews remove and replace the existing bridge.

FM 410, from US 82 to FM 3281. Watch for temporary lane and shoulder closures while crews install sidewalk and improve drainage.

CR 2127 at Scatter Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 1487, from FM 910 to FM 412. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.

FM 2120, from FM 2573 to FM SH 37. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.

Greenville Area (Hunt, Rains Counties)
Contacts: Greenville Area Office (903) 455-2363; Hunt Co. Maintenance (903) 455-2303; Rains Co. Maintenance (903) 473-2682.

Hunt County: SH 11, from Culver Street to Live Oak. The contractor has placed work zone signs and barricades. The contractor has begun milling for overlay operations to begin this week. The contractor has placed hot mix for turn lanes and intersections, curb work and sod placement will begin soon. This project is a traffic calming project and pedestrian improvements on SH 11. Please be aware of workers and watch for work zones when traveling in this area.
FM 1563, from SH50 to SH 2655: This is a 2.7-mile rehabilitation project that will widen the existing roadway. The contractor has set work zone signs and barricades. The contractor has begun preparing the right of way and placing some driveways and driveway safety-end-treatments. Please be aware of workers and watch for work zones when traveling in this area.
FM 2642, from FM 35 to SH 66: The contractor has set work zone signs and barricades. Excavation work for the detour is ongoing. The contractor has been performing saw cutting edge lines of the existing roadway for detour tie-ins. Crews worked on fine grading flex base. This contractor is performing detour work and backfilling edges. The contractor has begun demolition of median on the north end of I-30 intersection.
FM 2649, from I-30 to FM 1567. Contractors have set barricades and work zone traffic signs. Cross culvert work is complete, reworking the roadway, widening and cement treatment to the subgrade, and reworking the roadway base material is ongoing. The contractor is on mile six of this eight-mile project and will be hauling in flexbase material to begin processing and should start prime coat operations soon. Please be aware of workers and watch for work zones when traveling in this area.
Shelby Avenue Bridge: Greenville. The contractor has set barricades and work zone signage. The contractor has begun demolition of existing structure and will begin work on abutments. Contractor is waiting on beam fabrication, once complete beams will be placed soon. Please be aware of workers and watch for work zones when traveling in this area.
I-30 intersection improvements from Monte Stratton to FM 1903. The contractor has set barricades and advance warning signs. The contractor will be performing eastbound main lane widening and embankment placement. Utility work is ongoing in the area. The contractor plans to place more barrier and perform main lane widening work soon. Please be aware of workers and watch for work zones when traveling in this area.
Rains County: FM 2946, from FM 515 to FM 279. Contractors have set barricades and work zone traffic signs. The contractor is performing base repair work and widening work. Seal coat work and ditch work will be ongoing in this area. Please, be aware of workers and watch for work zones when traveling in this area.
Maintenance crews for both Hunt and Rains Counties will be performing various sign and mailbox installations on various roads. Both sections have been working on bridge maintenance projects. Herbicide operations are ongoing throughout both counties.

#