Paris District Road Report for week of January 15, 2024

Paris — Here’s a look at work planned in the district for the week starting Jan. 15, 2024. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay special attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

Sherman Area (Fannin, Grayson Counties)

Contacts: Sherman Area Office (903) 892-6529; Grayson Co. Maintenance (903) 893-8831; Fannin Co. Maintenance (903) 583-7566.

Safety Message: Click It or Ticket
“Click It or Ticket” is a TxDOT campaign urging Texans to buckle up. Currently 90.38 percent of Texans buckle up. However, in 2022, the number of people who died while not wearing a seat belt increased by 2.5 percent over 2021, with 1,258 unbuckled drivers and passengers killed on Texas roadways.
The National Highway Traffic Safety Administration estimates since its inception 21 years ago, “Click It or Ticket” has saved 7,399 lives, prevented more than 129,000 serious injuries and saved Texas more than $28.5 billion in related economic costs.
Wearing a seat belt reduces the risk of dying by 45 percent for people in the front seat of passenger cars. For those in pickups, seat belts reduce the risk of dying by 60 percent. Your seat belt is designed to keep you from being thrown into the dashboard or windshield—or even onto the road. An airbag can be a big lifesaver. But without a seat belt, it can be ineffective and even dangerous. In a crash, a seat belt ensures you’re not thrown into a opening airbag—a force that could injure or kill you. You may think your airbag is going to protect you, but it’s designed to work with seat belts, not to replace them.
In Texas, the law requires everyone in a vehicle to buckle up or face fines and court costs up to $200. Children younger than eight years must be in a child safety seat or booster seat unless they’re taller than four feet, nine inches. If they aren’t properly restrained, the driver faces fines up to $250, plus court costs.
Grayson County: US 75, from FM 1417 to SH 91 (Texoma Parkway). Watch for shoulder closures and lane shifts on the northbound and southbound US 75 main lanes between SH 91 and FM 1417 as crews work on building new main lanes, bridges, and retaining walls. Watch for lane closures on the frontage roads between FM 1417 and SH 91. A reduced speed limit of 60 mph on the US 75 mainlanes has been set on the mainlanes for this construction project.
Mainlane traffic has been switched from the old mainlanes to the existing frontage roads to allow for construction of the new mainlanes and bridges between South Travis Street and Center Street. During this operation, northbound US 75 mainlane traffic will shift onto the existing frontage road approximately one-half mile north of South Travis Street and transition back to the existing mainlanes at Middleton Street. Southbound US 75 mainlane traffic will shift onto the existing frontage road approximately one-half mile north of Park Avenue and transition back to existing mainlanes approximately one-half mile north of South Travis Street. This operation will allow for reconstruction of the proposed US 75 mainlanes and bridges at Post Oak Creek. During this phase, US 75 frontage road traffic will be reduced to a single travel lane while US 75 mainlane traffic will maintain two travel lanes. Both mainlane and frontage road traffic will be separated by concrete barriers.
All eastbound and westbound lanes of Park Avenue under US 75 are closed to traffic. This closure is necessary to allow for construction of the new overpass at Park Avenue. To detour, eastbound Park Avenue traffic will continue on the southbound US 75 frontage road, turn left on South Travis Street, and turn left on the northbound US 75 frontage road to return to Park Avenue. Westbound traffic will turn right on the northbound US 75 frontage road, turn left on Center Street, and turn left on the southbound US 75 frontage road to return to Park Avenue.
US 75, at the US 82 intersection. Watch for lane closures and lane shifts for the frontage roads on the northbound and southbound US 75 frontage road lanes between South Loy Lake Road and Lamberth Street, as well as on the eastbound and westbound US 82 frontage road lanes between FM 131 and Loy Lake Road while crews work on construction of new frontage road lanes.
FM 1417, from US 82 to SH 56. Watch for lane shifts and shoulder closures between US 82 and SH 56 while crews construct the new roadway pavement. The ultimate roadway will be a four-lane divided section with turn lanes. A reduced speed limit of 45 mph has been set for this construction project.
US 82, from SH 91 to FM 1417 in Sherman. Watch for lane closures as workers install a center median concrete barrier to help prevent crossover head-on collisions.
FM 121, from Main Street in Van Alstyne to SH 160. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
Park Road 20 in Eisenhower State Park. Watch for daytime lane closures within Eisenhower State Park as workers perform base repairs on the roadway and then overlay the roadway with a hot-mix surface. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
US 82, from the Cooke County line to FM 131 in Sherman. Watch for lane closures as workers replace the bridge railing and guardrail approaches at each bridge structure and install median barrier. During construction, bridge travel will be reduced to one lane while crews replace the bridge railing. Currently, the contractor is working on the westbound US 82 lanes at Harris Creek and on the eastbound lanes at Post Oak Creek. On this project, the contractor is also installing a center median concrete traffic barrier between FM 1417 and FM 131. Motorists should expect lane closures while this work is ongoing.
US 75 full depth concrete repair, from the Collin County line to the Oklahoma State line. Crews will be working on US 75 each week from Sunday night through Friday morning during the overnight period. Lane closures will be present at night for crews to replace failed concrete sections. Lane closures will begin at 7:30 p.m. each night and should be reopened to traffic by 6 a.m. This work will extend from the Collin-Grayson County line to the Oklahoma State line.
US 75 debris pickup, from Collin County line to Oklahoma State line. Watch for mobile lane closures as workers pick up debris from the roadway every Monday and Thursday during the nighttime.
FM 902, from US 377 to US 75. Watch for daytime lane closures as maintenance crews perform base repairs on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 3133, from SH 5 to the Collin County Line. Watch for daytime lane closures as maintenance crews perform base repairs on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 901, from FM 902 to SH 56. Watch for daytime lane closures as maintenance crews perform repair works on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Fannin County: SH 78, from US 82 to the Oklahoma State line. Watch for daytime shoulder closures and occasional lane closures as workers install sloped-end treatments on drainage structures and replace bridge rail and guardrail.
FM 100, from SH 56 to FM 2216. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 271, from SH 78 to FM 68. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
CR 3210 at Bullard Creek. CR 3210 at Bullard Creek is closed to through traffic to allow for replacement of the bridge. During the closure, traffic is asked to use CR 3200 as a detour.
CR 1020 at Caney Creek. CR 1020 at Caney Creek is closed to through traffic to allow for replacement of the bridge. During the closure, traffic is asked to use CR 1030 as a detour.
FM 981, from SH 78 to US 69. Watch for daytime lane closures as maintenance crews blade level the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 896, from Business SH 121 to US 69. Watch for daytime lane closures as maintenance crews blade level the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 1553, from SH 78 to SH 11. Watch for daytime lane closures as maintenance crews blade level the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.

Sulphur Springs Area (Hopkins, Franklin Counties):
Contacts: Sulphur Springs Area Office (903) 885-9514; Franklin Co. Maintenance (903) 537-4976; Hopkins Co. Maintenance (903) 885-4031.
Work on these projects is suspended through the Christmas holiday. Drive safely, drive friendly.
Franklin County: I-30, from SH 37 to County Road 3050. Watch for single lane closures and delays as crews grade ditches for truck parking area.
Hopkins County: FM 900, from I-30 to FM 3019. Watch for single lane closures and delays as crews perform surfacing operations.

Paris Area (Delta, Lamar, Red River Counties)
Contacts: Paris Area Office (903) 784-1357; Delta Co. Maintenance (903) 395-2139; Lamar Co. Maintenance (903) 785-4468; Red River Co. Maintenance (903) 427-3561.
Lamar County: Loop 286, from FM 1497 around the north loop to FM 1507. Watch for temporary lane and shoulder closures and traffic merges while crews improve guardrail and drainage structures and perform bridge maintenance.
Loop 286, from US 271 North going west to FM 79. Watch for temporary lane and shoulder closures, lane shifts, crossing closures and merging traffic while crews place a bonded concrete surface and perform asphalt paving operations.
US 271, from LP 286 to Oklahoma State Line. Watch for temporary lane and shoulder closures and traffic merges while crews resurface the pavement and perform bridge maintenance.
FM 1507 (Jefferson Rd), from SH 19 to 0.8 MI North of Loop 286. Watch for temporary lane and shoulder closures while crews install sidewalk.

CR 26320 at Morrison Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 1497, from FM 1184 to FM 3426. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures

SH 24, Lamar & Delta Counties: from the FM 64 intersection to 1,540 feet east of FM 198. Watch for temporary lane closures and lane shifts while crews resurface the roadway and perform bridge rail upgrades.

US 271, Lamar & Red River Counties: from the FM 196 North to SH 37. Watch for temporary shoulder closures and trucks entering and exiting the highway as crews remove tree and brush from within right of way.

Delta County: FM 64, from FM 128 to SH 1532. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.
FM 2068 at East Fork of Jernigan Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 2675, from Lamar County line to FM 128. Watch for temporary lane closures while crews rehabilitate the existing pavement and improve drainage structures.

Red River County: Cedar / Church Street (Clarksville, Texas), at the intersection of Cedar and Church Street. Watch for road closure while crews remove and replace the existing bridge.

Locust Street (Clarksville, Texas), at Delaware Creek. Watch for road closure while crews remove and replace the existing bridge.

FM 410, from US 82 to FM 3281. Watch for temporary lane and shoulder closures while crews install sidewalk and improve drainage.

CR 2127 at Scatter Creek. Watch for temporary roadway closure and detour while crews replace existing bridge structure.

FM 2120, from FM 2573 to SH 37. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.

FM 1487, from FM 910 to FM 412. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.

Greenville Area (Hunt, Rains Counties)
Contacts: Greenville Area Office (903) 455-2363; Hunt Co. Maintenance (903) 455-2303; Rains Co. Maintenance (903) 473-2682.

Hunt County: SH 11, from Culver Street to Live Oak. The contractor has placed work zone signs and barricades. The contractor has been working on signals at the various locations. The contractor has finished placing sod at various locations. Please be aware of workers and watch for work zones when traveling in this area.
FM 1563, from SH 50 to SH 2655: This is a 2.7-mile rehabilitation project that will widen the existing roadway. The contractor has set work zone signs and barricades. The contractor has begun preparing the right of way and placing driveways and driveway safety-end-treatments and cross culvert work in ongoing. The contractor is currently working on a culvert extension and performing subgrade widening work and base work. Please be aware of workers and watch for work zones when traveling in this area.
FM 2642, from FM 35 to SH 66: The contractor has set work zone signs and barricades. Excavation work for the detour is ongoing. The contractor has been performing saw cutting edge lines of the existing roadway for detour tie-ins. Crews worked on fine grading flex base. The contractor has shifted traffic to the West to begin removals of asphalt, concrete and some existing driveways. Placement of storm sewer has started. Please be aware of workers and watch for work zones when traveling in this area.
FM 2649, from I-30 to FM 1567. The contractors have set barricades and work zone traffic signs. Cross culvert work is complete. The contractor has completed subgrade widening and cement treatment of the subgrade near mile 6 of the 8-mile project. Riprap and erosion control work is ongoing in the area. Please be aware of workers and watch for work zones when traveling in this area.
Shelby Avenue and Bledsoe Creek Bridge: The contractor has set barricades and work zone signs at both locations. The contractor has placed beams and poured the concrete deck on Shelby Ave. The Bledsoe Creek in Fannin County project has begun on the backwalls and prep right-of-way work. Please be aware of workers and watch for work zones when traveling in this area.
I-30 intersection improvements from Monte Stratton to FM 1903. The contractor has set barricades and advance warning signs. The contractor will be performing eastbound mainlane widening and embankment placement. Utility work is ongoing. Temporary ramps are now opened. The contractor plans to place more barriers and perform main lane widening and drainage work in the area. Please be aware of workers and watch for work zones when traveling in this area.
Hunt and Rains Counties Maintenance crews will be performing various sign and mailbox installations on various roads. Both sections will be working on potholing. Both sections will be working on winter weather preparations.

#

new TXDOT EndTheStreakTX logo
new TXDOT EndTheStreakTX logo

www.txdot.gov | TxDOT on Facebook | TxDOT on Twitter

Author: Matt Janson

Share This Post On