Paris — Here’s a look at work planned in the district for the week starting February 10, 2025. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay special attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.
Safety Message: Impaired driving and penalties – DUI & DWI
Driving while under the influence of alcohol or drugs can risk your life and the lives of others, and it can send you to jail. If you are under 21, it is illegal for you to drive with any detectable amount of alcohol in your system.
When am I legally intoxicated?
You are legally intoxicated in Texas when your blood alcohol concentration reaches 0.08 percent, but you are breaking the law as soon as drugs or alcohol affect your driving — or flying or boating — ability.
What are the penalties for a DWI?
First offense
- Up to a $2,000 fine.
- Up to 180 days in jail upon conviction with three mandatory days.
- Loss of driver license up to a year.
Second offense
- Up to a $4,000 fine.
- One month to a year in jail upon conviction.
- Loss of driver license up to two years.
Third offense
- A $10,000 fine.
- Two to 10 years in prison.
- Loss of driver license up to two years.
These fines do not include a state fine of $3,000, $4,500, or $6,000 assessed upon sentencing.
Impaired driving with a child passenger
- You will be charged with child endangerment if you’re driving impaired with children under 15.
- You will be additionally fined up to $10,000.
- You could be put in jail for up to two years.
- You will lose your driver’s license for another 180 days.
Driving with an open container
Carrying an open container of alcohol in your vehicle, even if you’re not impaired, is illegal. Learn more about Texas open container laws.
Sherman Area (Fannin, Grayson Counties)
Contacts: Sherman Area Office (903) 892-6529; Grayson Co. Maintenance (903) 893-8831; Fannin Co. Maintenance (903) 583-7566.
Grayson County:
The annual crack seal contract to place sealant in the pavement cracks on roadways in Grayson County is underway. The following roadways will receive a crack seal: Spur 316 from SH 289 to FM 120, FM 120 in Denison from Houston Avenue to FM 1753, US 69 in Denison from Houston Avenue SH 56, FM 1417 from FM 691 to US 82, US 82 from FM 901 to FM 1417, US 82 frontage roads from FM 1417 to FM 1417, SH 56 from US 82 to SH 289, Spur 129 from US 377 to SH 56, FM 1417 from SH 56 to SH 11, SH 289 in Gunter from Kerfoot Road to Elm Street, FS 121 from FM 121 to the Denton County line, SH 5 in Van Alstyne from Redden Road to the Collin County line, SH 56 from SH 11 to FM 1417, SH 11 from SH 56 to FM 697, FM 902 in Tom Bean from SH 11 to King Street. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
US 75, from SH 91 (Texoma Parkway) to US 82. Construction on this project is expected to begin on February 19th. This project will rebuild the US 75 mainlanes from SH 91 to US 82 as well as reconstruct the entrance and exit ramps on US 75. The project will also reconstruct bridges at Taylor Street, Lamberth Street and the US 75 main lanes over US 82 and reconstruct the frontage road intersection at SH 91. A reduced speed limit of 60 mph on the US 75 mainlanes has been set for this construction project. Two lanes on the US 75 main lanes will remain open in each direction during the daytime hours with occasional further lane closures during the nighttime period. Watch for lane closures on the frontage roads during construction.
US 75, from US 82 to North Loy Lake Road. This project will rebuild and widen the US 75 mainlanes from four lanes to six lanes as well as reconstruct the entrance and exit ramps on US 75. The project will also reconstruct bridges at FM 691, Iron Ore Creek and Spur 503, and add U-turn bridges at Loy Lake Road in Sherman and Spur 503 in Denison. A reduced speed limit of 65 mph on the US 75 mainlanes has been set for this construction project. Watch for shoulder closures and lane shifts on the mainlanes of US 75 as well as frontage road lane closures within the project.
Westbound Spur 503 is closed to traffic near US 75 as the overpass to southbound US 75 has been removed to allow for construction of the new overpass. During this closure traffic on westbound Spur 503 will be required to detour onto the frontage road at the temporary exit ramp west of Theresa Drive and continue along the frontage road to the Loy Lake Road intersection where traffic can make the U-turn to continue south on the US 75 frontage road to the entrance ramp before the FM 691 intersection.
The U-turn lanes for the US 75 frontage roads at FM 691 are closed to traffic to allow crews to work on constructing the middle portion of the new US 75 bridge over FM 691. During this closure traffic wishing to make a U-turn at the intersection is asked to turn left onto FM 691 and make another left at the next signal light.
The exit ramp from northbound US 75 to North Loy Lake Road in Denison is closed permanently. Travelers who wish to access North Loy Lake Road from northbound US 75 will detour up to Crawford Street, make a U-turn at the Crawford Street intersection, and head south on the frontage road to reach North Loy Lake Road.
The westbound Spur 503 ramp to northbound US 75 is closed to traffic. A temporary detour is in place to divert this traffic onto the frontage road. Traffic will exit Spur 503 onto the frontage road using the new detour, continue along the Spur 503 frontage road which runs into the US 75 frontage road to the Loy Lake Road intersection. Traffic can continue along the frontage road through Loy Lake Road and then take the next entrance ramp to northbound US 75.
US 75, from FM 1417 to SH 91 (Texoma Parkway). A reduced speed limit of 60 mph on the US 75 mainlanes has been set on the mainlanes for this construction project. Watch for shoulder closures and occasional lane closures on the northbound and southbound US 75 main lanes between SH 91 and FM 1417 as crews work on completing the remaining work on this project. Watch for occasional lane closures on the frontage roads between FM 1417 and SH 91.
US 75, at the US 82 intersection. Watch for occasional lane closures for the frontage roads on the northbound and southbound US 75 frontage road lanes between South Loy Lake Road and Lamberth Street, as well as on the eastbound and westbound US 82 frontage road lanes between FM 131 and Loy Lake Road while crews work on completing the remaining work at the intersection.
SH 289, in Dorchester at the FM 902 intersection. Construction on this project is expected to begin on February 20th. This project will widen SH 289 on each side of the roadway to allow for the addition of a center left-turn lane. This project will also install traffic signals at this intersection. Motorists should expect delays during the daytime work hours as flaggers direct traffic through the work zone.
US 69, in Whitewright at the SH 11 and SH 160 intersection. This project will install traffic signals at this intersection. Watch for occasional daytime lane closures on US 69 and SH 11 as crews work to install the signal. Motorists should expect delays during the daytime work hours as flaggers direct traffic through the work zone.
SH 5, in Van Alstyne from Williams Way to Blassingame Avenue. Watch for daytime lane closures on SH 5 as crews work to install a shared use bicycle and pedestrian trail. The trail will follow along SH 5 from the existing trail at Williams Way to Blassingame Avenue, then along Tolson Avenue, then along Main Street where it will connect with Van Alstyne Parkway. Motorists should expect delays during the daytime work hours as flaggers direct traffic through the work zone.
US 377, from US 82 to the Oklahoma State line. Watch for daytime lane closures on US 377 as crews work to install rumble strips, backfill the pavement and seed the front slopes. Motorists should expect delays during the daytime work hours as pilot cars and flaggers direct traffic through the work zone.
FM 121, from Main Street in Van Alstyne to SH 160. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
US 82, from the Cooke County line to FM 131 in Sherman. Watch for lane closures as workers replace the bridge railing and guardrail approaches at each bridge structure and install median barrier. During construction, bridge travel will be reduced to one lane while crews replace the bridge railing. Currently, the contractor is working on the eastbound and westbound US 82 lanes at SH 56, and the eastbound and westbound US 82 lanes at the Union Pacific Railroad overpass. Watch for occasional daytime lane closures while workers perform bridge repairs.
US 75 debris pickup, from Collin County line to Oklahoma State line. Watch for mobile lane closures as workers pick up debris from the roadway every Sunday, Tuesday, and Thursday during the nighttime.
SH 56, from SH 11 to the Fannin County Line. Watch for daytime lane closures as maintenance crews perform spot milling on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 1417, from FM 691 to FM 120. Watch for daytime lane closures as maintenance crews perform a level up on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 1417 Proposed (East side of Sherman), from SH 56 to US 82. Watch for daytime lane closures as maintenance crews perform a level up on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Fannin County:
The annual crack seal contract to place sealant in the pavement cracks on roadways in Fannin County is underway. The following roadways will receive a crack seal: FM 2029 from FM 273 to FM 1396, FM 100 from FM 273 to FM 2216, FM 2216 from FM 100 to the Lamar County line, FM 1752 from US 82 to FM 898, SH 78 from US 82 to SH 56, Loop 205 from 9th Street to SH 56, SH 34 from SH 56 to FM 64, SH 11 from US 69 to the Hunt County line, FM 896 from Business SH 121 to US 69, FM 815 from Business US 69 to SH 78, US 69 from FM 896 to FM 272, and FM 1553 from SH 78 to SH 78. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
Bonham State Park, Park Road 24. Park Road 24 in the Bonham State Park will have daytime lane closures while crews rehabilitate the main road, camping spots and parking lots within the park. Detour routes will be present during construction to allow for the flow of traffic.
FM 68, at the North Sulphur River bridge. FM 68 at the North Sulphur River bridge is closed to through traffic as crews work on and replacing the bridge structure and roadway approaches. During the closure, traffic is asked to use SH 34, SH 11, and SH 78 as the detour route.
FM 2645, from FM 898 to FM 1753. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 274, from SH 78 to FM 1753. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 26 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
SH 121 overpass at US 69. The SH 121 overpass at US 69 is closed to thru traffic while crews perform bridge repairs. All traffic will be required to take the exit for US 69 and then will be able to take the next entrance ramp back onto SH 121. A temporary signal is in place to control traffic on SH 121 and US 69 during this closure. Motorists should expect delays as signals control traffic through the construction zone.
CR 1202 at Tributary of Brushy Creek. CR 1202 at Tributary of Brushy Creek has an onsite detour in place to allow for replacement of the bridge. Traffic is asked to approach the detour shift slowly and drive an appropriate speed through the work zone while crews replace the bridge structure.
CR 4020 at Caney Creek. CR 4020 at Caney Creek has been reopened to through traffic as construction on this project is now complete.
FM 68, from SH 78 to FM 271. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway to an overall width of 28 feet. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
SH 78, from US 82 to the Oklahoma State line. Watch for daytime shoulder closures and occasional daytime lane closures as workers install sloped-end treatments on drainage structures and replace bridge rail and guardrail.
FM 100, from SH 56 to FM 2216. Watch for daytime lane closures as crews work to rehabilitate and widen the roadway. Motorists should expect delays as signals and pilot cars direct traffic through the work zone.
FM 1550, from SH 34 to CR 3610. Watch for daytime lane closures as crews perform base repairs on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
FM 2815, from FM 1629 to SH 11. Watch for daytime lane closures as maintenance crews perform a level up on the roadway. Motorists should expect delays as flaggers and pilot cars direct traffic through the work zone.
SH 121, from SH 56 to SH 11. Watch for daytime lane closures as maintenance crews perform a sweeping operation to remove loose material from the roadway. Motorists should expect delays from the mobile operation in the work zone.
Sulphur Springs Area (Hopkins, Franklin Counties):
Contacts: Sulphur Springs Area Office (903) 885-9514; Franklin Co. Maintenance (903) 537-4976; Hopkins Co. Maintenance (903) 885-4031.
Hopkins County: SH 19, from I-30 to Rains County Line. Watch for crews performing drainage structure work. Expect slower moving traffic.
Hopkins County: Timber Creek Bridge. Watch for crews performing work on the roadway approach to the newly constructed bridge.
Hopkins County: IH 30, from Franklin County Line to Hunt County Line. Watch for crews performing bridge maintenance. Expect slower moving traffic.
Franklin County: SH 37, from US 67 to FM 71. Watch for crews performing joint sealing at bridge and guardrail locations. Watch for flaggers and slower moving traffic.
Franklin County: IH 30 Truck Parking. Watch for crews performing paving operations for the entrance and exits of the newly constructed Eastbound truck parking area. Expect slower moving traffic.
Paris Area (Delta, Lamar, Red River Counties)
Contacts: Paris Area Office (903) 784-1357; Delta Co. Maintenance (903) 395-2139; Lamar Co. Maintenance (903) 785-4468; Red River Co. Maintenance (903) 427-3561.
Lamar County:
Loop 286, from FM 1497 around the north loop to FM 1507. Watch for temporary lane and shoulder closures and traffic merges while crews improve guardrail and drainage structures and perform bridge maintenance.
FM 1497, from FM 1184 to FM 3426. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures
US 82 / Lamar Avenue, from 33rd street to 42nd street in Paris. Watch for temporary lane and shoulder closures in the nighttime hours while crews improve signals, install a raised center median, and resurface the roadway.
BU 271 B, from 18th Street SE to 34th Street SE . Watch for temporary lane and shoulder closures while crews install sidewalk on the north and south sides of the roadway.
SH 19/24, Lamar & Delta Counties: from LP 286 intersection to SH 19 . Watch for temporary lane closures and lane shifts while crews resurface the roadway, perform bridge rail upgrades, and bridge maintenance.
US 271, Lamar & Red River Counties: from FM 196 North to SH 37. Watch for temporary shoulder closures and trucks entering and exiting the highway as crews remove tree and brush from within right of way.
US 82, Lamar & Red River Counties: from State Loop 286 in Paris to Bowie County Line in Red River County. Watch for temporary lane and shoulder closures while crews improve drainage structures.
Delta County:
FM 2068 at East Fork of Jernigan Creek. The roadway is now reopened. Watch for temporary lane closures while crews replace existing bridge structure.
SH 24, at Doctor’s Creek. Watch for temporary shoulder closures and trucks entering and exiting the highway as crews perform bridge maintenance on the northbound structure.
SH 154, from SH 19 to BU 24. Watch for temporary lane and shoulder closures while crews improve drainage structures.
Red River County:
FM 2120, from FM 2573 to SH 37. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.
FM 1487, from FM 910 to FM 412. Watch for temporary lane and shoulder closures while crews rehabilitate the existing pavement and improve drainage structures.
Northeast Texas Trail, Clarksville, Texas. Watch for trucks and equipment entering and exiting streets and highways while crews construct the off-system trail.
Northeast Texas Trail, from BU 82J to Annona East City Limits. Watch for trucks and equipment entering and exiting streets and highways while crews construct the off-system trail.
BU 82 J at East Langford Creek. Watch for temporary roadway closure and detour while crews perform bridge maintenance operations.
Greenville Area (Hunt, Rains Counties)
Contacts: Greenville Area Office (903) 455-2363; Hunt Co. Maintenance (903) 455-2303; Rains Co. Maintenance (903) 473-2682.
Hunt County:
SH 11, from FM 2655 to SH 24. This project will add shoulders and replace drainage structures. The contractor has set barricades and is currently widening shoulders and performing ditch grading in the area. Excavation, flex base and flowable fill operations are ongoing. Work is currently ongoing at the Middle Sulphur River relief structure Mow strip work and metal beam guard fence work is ongoing. Please be aware of workers and watch for work zones when traveling in this area.
FM 1563, from SH 50 to SH 2655: This is a 2.7-mile rehabilitation project that will widen the existing roadway. The contractor has set work zone signs and barricades. Contractor is currently finishing cement treatment work on the second mile of the project and will begin prime coat and ride test soon. New guard rail placement is completed and work on mow strip is ongoing. Backfill work and slope work are ongoing near Bridge location. Fog seal work was completed on the first mile. Driveways are ongoing and are being completed by section of work. Please be aware of workers and watch for work zones when traveling in this area.
FM 2642, from FM 35 to SH 66: The contractor has set work zone signs and barricades. The contractor currently has paving operations and sidewalk operations ongoing. Contractor is forming rebar and working block outs for driveways near Peppergrass. Inlet prep work and installation are ongoing. Railroad coordination is underway near FM 2642 and SH 66, work will begin soon in this area. Traffic switch coordination is ongoing and signs will be placed soon alerting the traveling public. Please be aware of workers and watch for work zones when traveling in this area.
FM 512, From SH 34 to FM 118. The contractor has placed barricades and work zone traffic signs. The contractor has begun repair work on base and subgrade failures. The contractor has begun replacing culverts and bridge structures. Contractor graded ditches and set driveway and culvert pipes along with SET’s. Roadway reclamation has been completed for 3900 feet of the project. Reworking of base material is ongoing and drainage structure work is ongoing. Please be aware of workers and watch for work zones when traveling in this area.
I-30 intersection improvements from Monte Stratton to FM 1903. The contractor has set barricades and advance warning signs. The contractor has begun excavation at FM 1903 (West side) and working on placing wire wall at FM 1903 (East side) and soil nail walls at FM 1903.The contractor is also placing embankment & Wire walls east of 1570.along with form work for Bent #3 Cap at FM 1570. Beams will be set on FM 1570 WB on 2/6 and 2/7. There will be approximately (18) heavy trucks on 2/6 and (9) trucks on 2/7. The contractor will stage the trucks at Buccee’s in Royse City and bring them into Greenville, Tx. In order to make the WBML movement, they will need to turnaround at the IH 30 & SH 34/ Wesley St. Intersection. Please be aware of workers and watch for work zones when traveling in this area.
I-30 Improvements from CR2511 to FM 36: The contractor will be moving barrier during nighttime lane closures and milling shoulders. Contractor has ongoing box culvert work near FM 1565 plans to restore the frontage road pavement during this time. Temporary walls are being installed and dirt work with detours are ongoing throughout the project.
Hunt and Rains Counties Hunt County and Rains maintenance crews will be performing pothole and sign repair work throughout Hunt and Rains County.
Hunt and Rains County maintenance sections will be working on SH 66 and FM 36 in Caddo Mills to resurface a section of the highway with milling and inlay. Later a striping crew will restripe this area to add a left turn lane. Culvert work is ongoing at Division and IH 30 frontage roads. Work is also ongoing on FM 272 near Celeste for shoulder repair and level up. This work will be to aid travelers in this area at the intersection during peak travel times.
###