Sulphur Springs City Manager's Report For January 2020
Jan08

Sulphur Springs City Manager's Report For January 2020

Sulphur Springs City Manager Marc Maxwell Below is the City Manager’s Report reported by Marc Maxwell Jan. 7, to Sulphur Springs City Council. WASTEWATER TREATMENT PLANT Construction is complete with the exception of sowing grass seed which is ongoing. For all intents and purposes this project is complete. Budget for the project was $18,800,000. We expect total expenditures on the project to come in at $18,400,000. This project is...

Read More
City Manager's Report for December 2019
Dec05

City Manager's Report for December 2019

Below is the City Manager’s Report reported by Marc Maxwell Dec. 3, to Sulphur Springs City Council by Wastewater Treatment Plant The construction on all of the functional elements at the wastewater treatment plant is complete. All that remains is construction of the road. The plant is completely operational. Bellview Street The Bellview project has begun. Installation of sewer mains is ongoing. Connally Street The contractor on...

Read More
Sulphur Springs City Manager’s Report
Nov06

Sulphur Springs City Manager’s Report

MANAGER’S REPORT Presented to the City Council on Nov. 5, 2019 SUNSET STREET – The Capital Construction crew has installed 500’ of new curb and gutter, 5 new driveway approaches, 240’ of the concrete street, approach for Houston Street, asphalt for the tie-in at Finney Street and Van Sickle Street. The project is now complete. CONNALLY STREET – Approximately 2,150’ or 80% has been cement stabilized. The excavation is completed and...

Read More
Hopkins County Man Sentenced for Child Sexual Exploitation Violations
Oct04

Hopkins County Man Sentenced for Child Sexual Exploitation Violations

PLANO, Texas – A 53-year-old Sulphur Springs, Texas man has been sentenced to 17.5 years in federal prison for child exploitation violations in the Eastern District of Texas, announced U.S. Attorney Joseph D. Brown today. Russell Dean Hill pleaded guilty on May 3, 2019, to distributing child pornography and was sentenced to 210 months in federal prison by U.S. District Judge Sean D. Jordan on Oct. 2, 2019.  Upon his release from...

Read More
Sulphur Springs City Manager’s Report For Oct. 1, 2019
Oct02

Sulphur Springs City Manager’s Report For Oct. 1, 2019

Presented to the City Council by City Manager Marc Maxwell on Oct. 1, 2019 SUNSET STREET – This project is nearing completion. The Capital Construction Division is on the last segment of this street. You can see them setting forms for curb & gutter in the photo to the right. I expect them to finish in 3 weeks, as we will still need to tie-in some driveways. Work progresses on Sunset Street CONNALLY STREET – The contractor, 5W...

Read More
Sulphur Springs City Manager’s Report For Sept. 3, 2019
Sep04

Sulphur Springs City Manager’s Report For Sept. 3, 2019

Presented by Sulphur Springs City Manager Marc Maxwell during the Sept. 3, 2019 City Council meeting. Progress on street construction work SUNSET STREET – The Capital Construction Division is back at work on Sunset Street. We have changed the profile of the lay-down curbs to a gentler transition. This is a grant funded project through the Community Development Block Grant program. CONNALLY STREET – The contractor, 5W Contracting, has...

Read More
City Manager’s Report For Aug. 6, 2019
Aug07

City Manager’s Report For Aug. 6, 2019

PACIFIC PARK DRAINAGE PROJECT This project is progressing well. This project is finished. The barricades will remain in place until Friday so that the concrete will cure a bit more before we subject it to traffic. Allowing traffic on the concrete before it has had sufficient time to cure would lead to cracking and premature failure. The estimated final cost of the project is $43,000, well under the $85,000 budget. SUNSET STREET This...

Read More
City Manager’s Report Presented In July 2019 Council Meeting
Jul03

City Manager’s Report Presented In July 2019 Council Meeting

By Marc Maxwell, Sulphur Springs city manager PACIFIC PARK DRAINAGE PROJECT On Sept. 4, 2018, the City Council approved an expenditure of $85,000 to solve a drainage issue at Carter Street and Martin Luther King Jr. Drive. Since that time engineering has designed an alternative that is simpler and less expensive. It will be easier to maintain also. We have retained 5W Construction to perform the work. They plan to start next week....

Read More
City Manager’s Report Presented in February Council Meeting
Feb06

City Manager’s Report Presented in February Council Meeting

City Manager Marc Maxwell’s Report presented in the February City Council meeting included: CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds and Peavine Pinion Pond. In January the Capital Construction Division poured more concrete, installed bike racks and trash cans, laid sod to prevent erosion, installed a water fountain and planted trees. SUNSET STREET – Work should begin on this...

Read More
Sulphur Springs City Manager’s Report January 8, 2019
Jan09

Sulphur Springs City Manager’s Report January 8, 2019

CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds. The Capital Construction division installed 200 linear feet of pathway and a retaining wall on the Civic Center grounds. SUNSET STREET – We have been waiting for bids for the rock. They came in today. Now our grant writer will review the bids for compliance with the grant requirements. Once we approve the bids we will get started on the...