Sulphur Springs City Manager’s Report For Oct. 1, 2019
Presented to the City Council by City Manager Marc Maxwell on Oct. 1, 2019 SUNSET STREET – This project is nearing completion. The Capital Construction Division is on the last segment of this street. You can see them setting forms for curb & gutter in the photo to the right. I expect them to finish in 3 weeks, as we will still need to tie-in some driveways. Work progresses on Sunset Street CONNALLY STREET – The contractor, 5W...
Sulphur Springs City Manager’s Report For Sept. 3, 2019
Presented by Sulphur Springs City Manager Marc Maxwell during the Sept. 3, 2019 City Council meeting. Progress on street construction work SUNSET STREET – The Capital Construction Division is back at work on Sunset Street. We have changed the profile of the lay-down curbs to a gentler transition. This is a grant funded project through the Community Development Block Grant program. CONNALLY STREET – The contractor, 5W Contracting, has...
City Manager’s Report For Aug. 6, 2019
PACIFIC PARK DRAINAGE PROJECT This project is progressing well. This project is finished. The barricades will remain in place until Friday so that the concrete will cure a bit more before we subject it to traffic. Allowing traffic on the concrete before it has had sufficient time to cure would lead to cracking and premature failure. The estimated final cost of the project is $43,000, well under the $85,000 budget. SUNSET STREET This...
City Manager’s Report Presented In July 2019 Council Meeting
By Marc Maxwell, Sulphur Springs city manager PACIFIC PARK DRAINAGE PROJECT On Sept. 4, 2018, the City Council approved an expenditure of $85,000 to solve a drainage issue at Carter Street and Martin Luther King Jr. Drive. Since that time engineering has designed an alternative that is simpler and less expensive. It will be easier to maintain also. We have retained 5W Construction to perform the work. They plan to start next week....
City Manager’s Report Presented in May Council Meeting
City Manager Marc Maxwell’s Report presented in the May City Council meeting included: CROSSTOWN TRAIL – The Capital Construction Division constructed a retaining wall at Coleman Park. Otherwise, the project is on hold until Connally is done or nearly done. Retaining wall constructed at Coleman Park, part of the Crosstown Trail project SPRING CLEANUP – The annual spring cleanup was a successful event. In total, Sanitation...
City Manager’s Report Presented in February Council Meeting
City Manager Marc Maxwell’s Report presented in the February City Council meeting included: CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds and Peavine Pinion Pond. In January the Capital Construction Division poured more concrete, installed bike racks and trash cans, laid sod to prevent erosion, installed a water fountain and planted trees. SUNSET STREET – Work should begin on this...
Sulphur Springs City Manager’s Report January 8, 2019
CROSSTOWN TRAIL – Construction continues on the Hopkins County Civic Center grounds. The Capital Construction division installed 200 linear feet of pathway and a retaining wall on the Civic Center grounds. SUNSET STREET – We have been waiting for bids for the rock. They came in today. Now our grant writer will review the bids for compliance with the grant requirements. Once we approve the bids we will get started on the...
City Manager’s Report December 4, 2018
CROSSTOWN TRAIL – Construction continues on the Hopkin County Civic Center grounds. The Capital Construction division installed 317 linear feet of pathway on the Civic Center grounds. SUNSET STREET – We opened bids for materials for this project on October 24th. Of the 5 bid packets, we only had successful bids on 2 of them. We will have to rebid the remaining. WASTEWATER TREATMENT PLANT – Phase 2 is well under way....
City Manager’s Report to Council November 6, 2018
CROSSTOWN TRAIL – The flashing lights for the Main Street crossing have been installed and are now operational. The capital construction division installed 596 linear feet of sidewalk divided among Coleman Dam, Peavine Pinion Pond and the high school. SUNSET STREET – We opened bids for materials for this project on October 24th. Of the 5 bid packets, we only had successful bids on 2 of them. We will have to rebid the...
Sulphur Springs City Manager’s Report October 2, 2018
CANTEX FORCE MAIN – This project is completed. The Capital Construction division connected the final segment of sewer main to the Cantex Lift Station and began pumping through the new force main Monday night. This was the final capital improvement project in the 2013-2017 C.I.P. It replaces 2,400 linear feet of aging sewer force main and 2,900 feet of gravity main. The sewer main did pass through the middle of the hospital...